Completed the installation of preheating tower structures for the white cement plant project in the Republic of Bashkortostan

25 сентября 2019

Completed the installation of preheating tower structures for the white cement plant project in the Republic of Bashkortostan

On September 20, 2019, the installation of building structures for a preheating tower with a cyclone heat exchanger was completed at the White Cement Plant in the Republic of Bashkortostan, which is being built by Sinoma for the Austrian company Lasselsberger. The installation of metal structures for the preheating tower began on July 10 and was fully completed on September 20. Therefore, the total installation time was only 72 days, which is the result of the well-coordinated work of the Sinoma project team on site. The white cement plant for Lasselsberger will be the second in Russia to produce white cement. The contract for the construction of the EPC plant was concluded with Sinoma in 2018.